Career In Industrial Engineering Listed Chronologically.

Mountaintop Baking:  July 2002 to November 2002

Provide tracking of plant operations and efficiency.

  • Created new methods of tracking plant performance.
  • Evaluation of projects for internal rate of return.
  • Performed labor studies that aided in project decision making.

Stork GAMCO: June 2001 to December 2001

  • layouts for new equipment using Auto-CAD 14.
  • Created new process center with material handling specifications.
  • Correct and update routings in AS400 database

Leggett & Platt, Inc.:  December 2000 to April 2001

Perform time studies, bills of materials, routings, capital justifications, pack documentation in a metal stamping environment.

  • Saved $4,870 by justifying new die to improve process.
  • Reduced labor costs by $3000 by implementing material handling equipment.
  • Reduction of product damage in shipping by introducing new packaging.
  • Increase of small part throughput by 20,000 parts per hour at paint line.

ESAB Welding and Cutting:  March 1999 to September 1999

Involvement in new product introduction, assembly cell setup, process design, tooling requirements, bills of materials, routings, process FMEAS for assembly environment.

  • Full introduction of 12 new products.
  • Savings of $200 per product by correcting bills of material.
  • Created new tooling to eliminate damage to product components during assembly.
  • Creation of new training materials to reduce potential assembly errors.

 

Marley Electric Heating:  February 1998 to January 1999

Work in teams for Kaizen events, line balancing, time studies, SMED, cell layout, ergonomics, implementation of  lean manufacturing concepts in a metal stamping and assembly environment. 

  • Reduction of metal coil press setup time by 30 minutes
  • Participated in bringing company to ISO certification.
  • Increased product output by setting takt time.